For construction photos and videos, please select a project using the Construction drop down menu in the main navigation.
The SRWA Design Build team celebrated a big milestone recently — the team has worked 250,000 man hours without a lost time accident.


Current Road Closures
- There are currently no road closures associated with the project.
Please drive safely in construction zones.
Week of February 6, 2023
Water Treatment Plant
- Site Grading, backfilling Duct banks and Placing concrete for Light pole bases.
- Installing AT&T electrical conduit along the TID canal from Geer Road to the Water Treatment Plant.
- Installing veneer block and roofing on the outside and continuing to install plumbing and electrical inside the Administration and Operations building.
- Installing plumbing and electrical rough ins and cable trays and adding exterior trim work at the Maintenance and Repair building.
- Applying coatings in the containment area, taping sheet rock in the electrical room, and continuing to install cable trays and
plumbing rough ins at the Chemical Storage building.
- Packing grout under the base plates and grading around the building at the Finished Water Pump station building.
- Patch work on the exterior concrete at the Flocculation Sedimentation structure.
- Installing handrails, stairs and gratings for the Back Wash Equalization structure.
- Laying out handrails, injecting epoxy into concrete walls and performing leak tests at the Ozone Contactors structure.
- Installing interior electrical work, pulling wire and making connections between interior panels at the Ozone Building.
- Performing pipe fit ups at the Flow Split Facility.
- Demolishing existing concrete irrigation lines, placing concrete for the wing walls at Aldrich bridge, installing metals and grating in front of the openings for the Raw Water
Outfall structure.
Turlock Finished Water Transmission Main
- No work is scheduled at this site this week.
Raw Water Transmission Main
- No work is scheduled at this site this week.
Ceres Finished Water Transmission Main
- No work is scheduled at this site this week.
Raw Water Pump Station
- Performing prep work for future electrical rough ins, concrete slab and sheet rock installation at the Raw Water Pump Station.