For construction photos and videos, please select a project using the Construction drop down menu in the main navigation.
The SRWA Design Build team celebrated a big milestone recently — the team has worked 250,000 man hours without a lost time accident.


Current Road Closures
- North Quincy is closed this week between E. Zeering and E.Monte Vista
- Berkeley will be closed south of Santa Fe to Barnhart
Please drive safely in construction zones and follow the posted detours.
Week of June 20, 2022
Water Treatment Plant
- Concrete Masonary Units (CMU) are being placed this week at the Administration Building
- Concrete pours at the Ozone Facility
- Electricians are installing under slab conduits at the Chemical Storage Building
Turlock Finished Water Transmission Main
- The contractor continues to grout the inside of the pipe
Raw Water Transmission Line
- No work is scheduled at this site this week.
Ceres Finished Water Transmission Main
- The contractor is working on the Flow Meter Vault at the Ceres Tank site this week
Raw Water Pump Station
- The contractor is installing electrical vaults and conduits this week.