Click the months below to filter through construction photos.
December
The last Plate Settler was placed today.
Concrete placement at the Ozone Contactors Bldg.
Insulated wall paneling being installed at the Raw Water Pump Station.
Flocculation Sedimentation structure Plate Settler hoisted down with a crane
Pipe Gallery at the Ozone Contactors
Maintenance Bldg.
Last section of pipe to Tie in.
November
Finish Water Pump Station
Chemical Storage
Ozone Contactors Pipe Gallery
Infiltration Gallery rebar inspection.
Motor Control Center (MCC’s) installed at the Ozone Bldg.
Maintenance Bldg.
Finish water Pump station metal Bldg.
Vertical Turbine pump assembly
Maintenance Bldg. Under construction
The first sheet rock installed in the Ozone Building
Metal stud framing in the Operations Bldg.
Canopy at the Chemical Storage structure.
Slab On Grade prep work at the Finish Water Pump Station
October
Inside the Sedimentation Basin
Maintenance Bldg. Under construction
Operations Bldg. metal stud framing.
Lime Silo.
Concrete placement at the Chemical Storage
Metal stud framing in the Operations Bldg
Maintenance Bldg
Insulated wall panels installed at the Ozone building
Maintenance building
Electrical duct banks
Meta stud framing in the Operations building
Rebar and formwork at the Chemical Storage facility
Duct bank installation
Prep work for Fire proofing in the Operations Building
Maintenance Building work in progress
Chemical Storage tanks delivered to the site.
Electrical conduits installed at the Flocculation Sedimentation structure.
Electrical duct banks
Work on the Maintenance Building continues
September
The Chem. Storage Building had it’s slab placed last week. They’re cleaning it up and stripping formwork.
The Electricians have been roughing in conduits, unistrut, and installing duct banks between vaults.
The Ozone Bldg. has metal framing and roof being erected
Drying beds Sand media being placed and spread. This is the final layer of material to be placed at this location.
Chemical Storage Formwork and rebar installation has been completed. Concrete to be placed on 9-21 and it will be 650 yards of concrete.
Underground piping and dirt moving taking place
Rebar and form work for Chemical Vault
August
Work currently taking place at the Administration / Operations building
Work currently taking place at the Administration / Operations building
Work currently taking place at the Administration / Operations building
Work currently taking place at the Administration / Operations building
Administration bldg.
Concrete placement for a Chemical Vault.
Administrative Operations bldg.
July
Back fill on the north side of the water storage tank. The vertical pipes are pump cans.
Administrative/ Operations Bldg. CMU (concrete masonry unit) Block construction continues. Administrative/ Operations Bldg. CMU (concrete masonry unit) Block construction continues.
Formwork, rebar installed for Lime silo slab.
Electrical work at the Chemical Storage Electrical room.
Ozone Contactors Structure
Open cut trench for Process piping between the Backwash Equalization and Flocculation Sedimentation structures.
36” raw water piping being welded on site. This pipe comes from the Flow split and is headed to the Flocculation Sedimentation structure
Administrative/Operations building. Contractor is working on the final lift of block and soon the structural steel roof framing will begin.
Administrative/ Operations on the South side
Block being installed at the Administrative/ Operations bldg.
Pump cans at Water Storage Tank - July 21
Process piping around site installed.
June
Ozone electrical room
Pump cans at the Water Storage Reservoir
Ozone Contactors Building
Rebar installation at the Flocculation Sedimentation deck.
Backfill at the 36” raw water line coming from the Flow split to the Flocculation Sedimentation building
Backfill on the north side of the water storage tank around the Pump cans
Formwork for Lime Silo concrete slab.
Concrete masonry units (CMU) being installed at the Administrative bldg.
Block construction underway at the Administrative/operations building
Construction continues at the Ozone Building . Wall forming, rebar installation.
Backfill around the Pump cans and water storage tank
Process piping being installed.
In place density testing at the water storage tank. As the dirt is backfilled it gets compacted and tested.
Block being installed at the Administrative/Operations building
Interior view of the rebar and framework for the Flocculation sedimentation tank.
Process piping being lined up and welded with the canned motor pumps for the Clearwell shown in the background.
Pump cans at water storage tank
Pump cans at the water storage tank on June 16
May
Ozone Building under construction
Water storage tank
The contractor is roughing in conduits in the Ozone Filters Electrical room
Electrical Vaults being installed at the Raw Water Pump Station.
Completed Outfall structure. This structure was built when the TID canal was empty and had to be completed prior to irrigation season.
Water storage tank and Manifold piping being connected.
Ozone Contactors and Filters Building
Placing concrete at the Administrative Building
Backfilling at the water storage tank
Installing wall forms at the Ozone Contactors Building
Rebar curtains being set via crane at the Ozone Contactors
April
Vapor barrier installation at the Administration Building
Construction activity at the Flocculation Sedimentation building
Ozone filters building wall formwork
Electrical room at Ozone Filters Building
North side of Flocculation Sedimentation building
Back Wash Equalization structure
Electrical room rough in for Ozone Contactors building.
Installing rebar mat for wall on East side of Ozone Contactors building.
March
Work underway at the Flocculation Sedimentation Building
Sand Media being placed at the drying beds.
Rebar install at the Ozone Building
Septic System Tank
Formwork and rebar installation at the Ozone Building
Work underway at the Flocculation Sedimentation Building
3. Ozone Filters Bldg. rebar installation With the Clearwell in the background.
Concrete pump placing concrete at the Flocculation Sedimentation Building
A conveyor belt being used to spread rock/sand at the Drying Beds
Aerial view of the work underway at the Water Treatment Plant
Aerial view of the work underway at the Water Treatment Plant
February
Filter slab, installation prior to concrete being placed
Electrical conduits for the administration building
Sludge drying bed drainage layer installation
Under slab conduit installation at the Maintenance Building
Rebar and form installation at the Flocculation Sedimentation Facility
Work under way at the Filter Building
installing drain rock and bed piping at the sludge drying beds
Rebar installation and electrical work underway at the water treatment plant.
Waterproof coating being applied to the Water Storage Tank
Drying bed liners
January
Drying beds liner.
Drying beds liner.
Moving forms at the Flocculation Sedimentation Building
Under slab plumbing at the Chemical Storage Building
Drying beds liner.
Ozone building rebar for concrete slab.
Ozone building rebar installation
Rebar installation at the Ozone Building
Wall placement #2 at the Flocculation Sedimentation facility
Back wash equalization tank constructed and full of water
Ozone Contactors and Filters Installation underway. Underground piping is in, subgrade and the rock section are compacted.
Water storage tank
Ozone building. sub-grade and rock section installation
Chemical Storage and Feed Building. Sub grade is in and base course (rock section) is being compacted.
Maintenance building
Under slab electrical and plumbing drains being installed in the Administrative building
Flocculation Sedimentation Structure
Picture from the Deck at the Back Wash Equalization Building
Outfall Structure (in the TID canal)
Rebar placement for the bottom mat at the Ozone Building
42” FTWM through canal at old Aldrich bridge location. Bridge in the photo is the new Aldrich bridge
Aerial view of the work underway at the Water Treatment Plant- January 2022
Aerial view of the work underway at the Water Treatment Plant- January 2022
Aerial view of the work underway at the Water Treatment Plant- January 2022
Aerial view of the work underway at the Water Treatment Plant- January 2022
Outfall structure
Search results
Website Accessibility Statement
Stanislaus Regional Water Authority (the "District") is committed to ensuring that its services are accessible to all
members of the public. As part of this commitment, the District strives to provide an accessible website compatible with
the Web Content Accessibility Guidelines (WCAG) version 2.1, AA, and commercial screen reading software. Features of the
website are created to allow individuals with vision and other impairments to understand and use the website to the same
degree as someone without disabilities.