The Chem. Storage Building had it’s slab placed last week. They’re cleaning it up and stripping formwork.
The Electricians have been roughing in conduits, unistrut, and installing duct banks between vaults.
The Ozone Bldg. has metal framing and roof being erected
Drying beds Sand media being placed and spread. This is the final layer of material to be placed at this location.
Chemical Storage Formwork and rebar installation has been completed. Concrete to be placed on 9-21 and it will be 650 yards of concrete.
Underground piping and dirt moving taking place
Rebar and form work for Chemical Vault