Ozone Building under construction
The contractor is roughing in conduits in the Ozone Filters Electrical room
Electrical Vaults being installed at the Raw Water Pump Station.
Completed Outfall structure. This structure was built when the TID canal was empty and had to be completed prior to irrigation season.
Water storage tank and Manifold piping being connected.
Ozone Contactors and Filters Building
Placing concrete at the Administrative Building
Backfilling at the water storage tank
Installing wall forms at the Ozone Contactors Building
Rebar curtains being set via crane at the Ozone Contactors